Project Title:

Rebuilding Primary School in Entebbe, Uganda

Project Overview

Rebuilding a little primary school in Entebbe, to provide a safe and conducive learning environment for 50 students.

Objectives Location Timeline
  1. Rebuild 2 classrooms and 1 office block.
  2. Construct 2 toilet blocks and 1 water harvesting system.
  3. Provide furniture, teaching materials, and equipment.

Entebbe, Uganda

  1. Needs assessment and planning: 1 month.
  2. Construction: 4 months.
  3. Completion and handover: 1 month.

Budget

  1. Construction materials: $7,000.
  2. Labor costs: $2,000.
  3. Furniture and equipment: $2,000.
  4. Contingency funds: $1,000.

Total budget: $12,000.

Implementation

  1. Recruit local construction workers.
  2. Source materials and equipment from local suppliers.
  3. Monitor and evaluate project progress.

Sustainability:

Establish a School Management Committee to oversee school operations and maintenance.